Bill of Quantities
Foundations
Project ID: 46 - Foundation 1
| Item No. | Description | Unit | Quantity | Rate (Ksh) | Total (Ksh) |
|---|---|---|---|---|---|
| 1. Excavation | |||||
| 1.1 | Strip Footing Excavation | m³ | 31.32 | 0.00 | 0.00 |
| 1.2 | Pad Footing Excavation | m³ | 0.00 | 0.00 | 0.00 |
| Total Excavation | 0.00 | ||||
| 2. Concrete Works | |||||
| 2.1 | Strip Footing Concrete | m³ | 5.22 | - | 41,760.00 |
| 2.2 | Pad Footing Concrete | m³ | 0.00 | - | 0.00 |
| Total Concrete | 41,760.00 | ||||
| 3. Reinforcement | |||||
| 3.1 | Strip Footing Bars | kg | 0.00 | - | 0.00 |
| 3.2 | Pad Footing Bars | kg | 0.00 | - | 0.00 |
| Total Reinforcement | 0.00 | ||||
| 4. Masonry | |||||
| 4.1 | Bricks | Pieces | 842 | 30.00 | 25,260.00 |
| 5. Mortar | |||||
| 5.1 | Mortar Volume | m³ | 4.09 | 8,000.00 | 32,755.84 |
| 6. Summary | |||||
| 6.1 | Total Cement Bags | Bags | 50.96 | - | - |
| 6.2 | Total Fine Aggregates (Sand) | Lorries | 1.33 | - | - |
| 6.3 | Total Coarse Aggregates (Ballast) | Lorries | 0.56 | - | - |
| 6.4 | Labor | - | - | - | 29,932.75 |
| 6.5 | Material Cost | - | - | - | 99,775.84 |
| Total Cost | 129,708.59 | ||||
| Edit | |||||
Ground Floor
Walls
Add Wall ItemSummary Totals
Total Cement Bags: 80.03
Total Sand (FSR Lorry): 2.08
Total Bricks: 2,057.00
Total Brick Cost: Ksh 82,280.00
Total Mortar Cost: Ksh 88,920.32
Total Labor Cost: Ksh 68,160.10
Grand Total Cost: Ksh 295,360.42
Interior Walls With Doors
No interior walls created.
Total Walls Analysis (Including Exterior Walls)
Total Cement Bags: 80.03
Total Fine Aggregate (FSR Lorry): 2.08
Total Bricks: 2,057.00
Total Bricks Cost: Ksh82,280.00
Total Mortar Cost: Ksh88,920.32
Total Walls Cost: Ksh295,360.42
Slab Panels
No slabs created.
Beams
Create Beam
Beam: Beam 1 (ID: 46)
| Item Description | Unit | Quantity | Rate (Ksh) | Total (Ksh) |
|---|---|---|---|---|
| Concrete Works | ||||
| Concrete Volume | m³ | 2.61 | - | - |
| Cement Bags | Bags | 10.74 | - | - |
| Fine Aggregates (Sand) | Lorry | 0.28 | - | - |
| Coarse Aggregates (Ballast) | Lorry | 0.28 | - | - |
| Concrete Cost | m³ | 2.61 | 6,000.00 | 15,660.00 |
| Reinforcement | ||||
| Main Bars (12mm Ø) | bars | 9.67 | - | 14,418.00 |
| Support Bottom Bars (0mm Ø) | bars | 0.00 | - | 0.00 |
| Top Bars (12mm Ø) | bars | 9.67 | - | 14,418.00 |
| Support Top Bars (0mm Ø) | bars | 0.00 | - | 0.00 |
| Links (8mm Ø) | bars | 14.58 | - | 9,661.78 |
| Total Reinforcement Cost | kg | 274.99 | 140.00 | 38,497.99 |
| Labor & Formwork | ||||
| Labor | Sum | 1 | - | 23,294.40 |
| Formwork | Sum | 1 | - | 23,490.00 |
| Total Material Cost | 77,647.99 | |||
| Grand Total | 100,942.38 | |||
Total Cost for All Beams: Ksh 100,942.38
Columns
No columns created.
Hipped Roofs
No hipped roof data available.
Gable Roof
Grand Total Cost Summary
Grand Cement Bags:
141.72
Grand Fine Agg (Sand) FSR Lorry:
Ksh 3.69
Grand Coarse Agg (Ballast) FSR Lorry:
Ksh 0.84
Grand Concrete Cost:
Ksh 57,420.00
Grand Bars Cost:
Ksh 38,497.99
Grand Labor Cost:
Ksh 228,433.17