Bill of Quantities
Foundations
Project ID: 46 - Foundation 1
Item No. | Description | Unit | Quantity | Rate (Ksh) | Total (Ksh) |
---|---|---|---|---|---|
1. Excavation | |||||
1.1 | Strip Footing Excavation | m³ | 28.80 | 250.00 | 7,200.00 |
1.2 | Pad Footing Excavation | m³ | 0.00 | 0.00 | 0.00 |
Total Excavation | 7,200.00 | ||||
2. Concrete Works | |||||
2.1 | Strip Footing Concrete | m³ | 4.80 | - | 60,720.00 |
2.2 | Pad Footing Concrete | m³ | 0.00 | - | 0.00 |
Total Concrete | 60,720.00 | ||||
3. Reinforcement | |||||
3.1 | Strip Footing Bars | kg | 0.00 | - | 0.00 |
3.2 | Pad Footing Bars | kg | 0.00 | - | 0.00 |
Total Reinforcement | 0.00 | ||||
4. Masonry | |||||
4.1 | Bricks | Pieces | 775 | 40.00 | 31,000.00 |
5. Mortar | |||||
5.1 | Mortar Volume | m³ | 3.22 | 8,000.00 | 25,782.02 |
6. Summary | |||||
6.1 | Total Cement Bags | Bags | 42.95 | - | - |
6.2 | Total Fine Aggregates (Sand) | Lorries | 1.12 | - | - |
6.3 | Total Coarse Aggregates (Ballast) | Lorries | 0.51 | - | - |
6.4 | Labor | - | - | - | 37,410.60 |
6.5 | Material Cost | - | - | - | 124,702.02 |
Total Cost | 162,112.62 | ||||
Edit |
Ground Floor
Project ID: 46
Description | Unit | Quantity | Unit Rate (Ksh) | Total (Ksh) |
---|---|---|---|---|
Substructure | ||||
Hardcore Blinding | m³ | 28.80 | 1,000.00 | 28,800.00 |
Murram Blinding | m³ | 0.00 | 0.00 | 0.00 |
Damp Proof Course (DPC) | Item | 1 | 0.00 | 0.00 |
BRC Mesh | Item | 1 | 0.00 | 0.00 |
Concrete Work | ||||
Concrete Work | m³ | 10.80 | 12,650.00 | 136,620.00 |
Screed Mortar | m³ | 2.88 | 8,000.00 | 23,040.00 |
Total Cement Bags | Bags | 65.17 | - | - |
Total Fine Aggregates (Sand) | Lorries | 1.70 | - | - |
Total Coarse Aggregates (Ballast) | Lorries | 1.16 | - | - |
Finishes | ||||
Floor Tiles | Pcs | 1,600.00 | 135.00 | 216,000.00 |
Other Costs | ||||
Labor | Item | 1 | 121,338.00 | 121,338.00 |
Total Material Cost | Item | 1 | 404,460.00 | 404,460.00 |
Total Cost | 525,798.00 |
Walls
Add Wall ItemSummary Totals
Total Cement Bags: 210.74
Total Sand (FSR Lorry): 5.49
Total Bricks: 5,367.00
Total Brick Cost: Ksh 214,680.00
Total Mortar Cost: Ksh 234,151.42
Total Labor Cost: Ksh 168,849.43
Grand Total Cost: Ksh 731,680.85
Interior Walls With Doors
No interior walls created.
Total Walls Analysis (Including Exterior Walls)
Total Cement Bags: 210.74
Total Fine Aggregate (FSR Lorry): 5.49
Total Bricks: 5,367.00
Total Bricks Cost: Ksh214,680.00
Total Mortar Cost: Ksh234,151.42
Total Walls Cost: Ksh731,680.85
Slab Panels
No slabs created.
Beams
Create Beam
Beam: Beam 1 (ID: 46)
Item Description | Unit | Quantity | Rate (Ksh) | Total (Ksh) |
---|---|---|---|---|
Concrete Works | ||||
Concrete Volume | m³ | 6.00 | - | - |
Cement Bags | Bags | 24.69 | - | - |
Fine Aggregates (Sand) | Lorry | 0.64 | - | - |
Coarse Aggregates (Ballast) | Lorry | 0.64 | - | - |
Concrete Cost | - | - | - | 75,900.00 |
Reinforcement | ||||
Main Bars (10mm Ø) | kg | 4.00 | - | 481.00 |
Support Bottom Bars (0mm Ø) | kg | 0.00 | - | 0.00 |
Top Bars (10mm Ø) | kg | 4.00 | - | 481.00 |
Support Top Bars (0mm Ø) | kg | 0.00 | - | 0.00 |
Links (8mm Ø) | kg | 197.69 | - | 25,699.26 |
Total Reinforcement Cost | 205.09 | 26,661.06 | ||
Labor & Formwork | ||||
Labor | Sum | 1 | - | 35,568.32 |
Formwork | Sum | 1 | - | 16,000.00 |
Total Material Cost | 118,561.06 | |||
Grand Total | 154,129.37 |
Beam: Beam 1 (ID: 46)
Item Description | Unit | Quantity | Rate (Ksh) | Total (Ksh) |
---|---|---|---|---|
Concrete Works | ||||
Concrete Volume | m³ | 10.50 | - | - |
Cement Bags | Bags | 43.20 | - | - |
Fine Aggregates (Sand) | Lorry | 1.13 | - | - |
Coarse Aggregates (Ballast) | Lorry | 1.13 | - | - |
Concrete Cost | - | - | - | 132,825.00 |
Reinforcement | ||||
Main Bars (10mm Ø) | kg | 4.00 | - | 481.00 |
Support Bottom Bars (0mm Ø) | kg | 0.00 | - | 0.00 |
Top Bars (10mm Ø) | kg | 4.00 | - | 481.00 |
Support Top Bars (0mm Ø) | kg | 0.00 | - | 0.00 |
Links (8mm Ø) | kg | 336.07 | - | 43,688.74 |
Total Reinforcement Cost | 343.47 | 44,650.54 | ||
Labor & Formwork | ||||
Labor | Sum | 1 | - | 59,242.66 |
Formwork | Sum | 1 | - | 20,000.00 |
Total Material Cost | 197,475.54 | |||
Grand Total | 256,718.20 |
Total Cost for All Beams: Ksh 410,847.57
Columns
No columns created.
Hipped Roofs
No hipped roof data available.
Gable Roof
Grand Total Cost Summary
Grand Cement Bags:
386.75
Grand Fine Agg (Sand) FSR Lorry:
Ksh 10.07
Grand Coarse Agg (Ballast) FSR Lorry:
Ksh 3.44
Grand Concrete Cost:
Ksh 269,445.00
Grand Bars Cost:
Ksh 71,311.59
Grand Labor Cost:
Ksh 468,075.04