Menu

Bill of Quantities

Foundations

Project ID: 46 - Foundation 1

Item No. Description Unit Quantity Rate (Ksh) Total (Ksh)
1. Excavation
1.1 Strip Footing Excavation 28.80 250.00 7,200.00
1.2 Pad Footing Excavation 0.00 0.00 0.00
Total Excavation7,200.00
2. Concrete Works
2.1Strip Footing Concrete4.80-60,720.00
2.2Pad Footing Concrete0.00-0.00
Total Concrete60,720.00
3. Reinforcement
3.1Strip Footing Barskg0.00-0.00
3.2Pad Footing Barskg0.00-0.00
Total Reinforcement0.00
4. Masonry
4.1BricksPieces77540.0031,000.00
5. Mortar
5.1Mortar Volume3.228,000.0025,782.02
6. Summary
6.1Total Cement BagsBags42.95--
6.2Total Fine Aggregates (Sand)Lorries1.12--
6.3Total Coarse Aggregates (Ballast)Lorries0.51--
6.4Labor---37,410.60
6.5Material Cost---124,702.02
Total Cost 162,112.62
Edit

Ground Floor

Project ID: 46

Description Unit Quantity Unit Rate (Ksh) Total (Ksh)
Substructure
Hardcore Blinding 28.80 1,000.00 28,800.00
Murram Blinding 0.00 0.00 0.00
Damp Proof Course (DPC) Item 1 0.00 0.00
BRC Mesh Item 1 0.00 0.00
Concrete Work
Concrete Work 10.80 12,650.00 136,620.00
Screed Mortar 2.88 8,000.00 23,040.00
Total Cement Bags Bags 65.17 - -
Total Fine Aggregates (Sand) Lorries 1.70 - -
Total Coarse Aggregates (Ballast) Lorries 1.16 - -
Finishes
Floor Tiles Pcs 1,600.00 135.00 216,000.00
Other Costs
Labor Item 1 121,338.00 121,338.00
Total Material Cost Item 1 404,460.00 404,460.00
Total Cost 525,798.00
Edit

Walls

Add Wall Item
Item Description Unit Quantity Rate (Ksh) Amount (Ksh) Actions
1 Bricks for Wall1 No. 5,367 40.00 214,680.00
2 Mortar (Volume: 29.269 m³) 29.269 8,000.00 234,151.42
3 Cement Bags for Mortar Bags 210.74 - -
4 Sand (Fine Aggregate) - Lorry (FSR) Lorry 5.49 - -
5 Windows (Type 1: 8, Type 2: 0) No. 8.00 - 64,000.00
6 Doors (Type 1: 2, Type 2: 5) No. 7.00 - 50,000.00
Total Cost for Wall1 Ksh 731,680.85

Summary Totals

Total Cement Bags: 210.74

Total Sand (FSR Lorry): 5.49

Total Bricks: 5,367.00

Total Brick Cost: Ksh 214,680.00

Total Mortar Cost: Ksh 234,151.42

Total Labor Cost: Ksh 168,849.43

Grand Total Cost: Ksh 731,680.85

Interior Walls With Doors

No interior walls created.

Total Walls Analysis (Including Exterior Walls)

Total Cement Bags: 210.74

Total Fine Aggregate (FSR Lorry): 5.49

Total Bricks: 5,367.00

Total Bricks Cost: Ksh214,680.00

Total Mortar Cost: Ksh234,151.42

Total Walls Cost: Ksh731,680.85

Slab Panels

No slabs created.

Beams

Create Beam
Beam: Beam 1 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 6.00 - -
Cement Bags Bags 24.69 - -
Fine Aggregates (Sand) Lorry 0.64 - -
Coarse Aggregates (Ballast) Lorry 0.64 - -
Concrete Cost - - - 75,900.00
Reinforcement
Main Bars (10mm Ø) kg 4.00 - 481.00
Support Bottom Bars (0mm Ø) kg 0.00 - 0.00
Top Bars (10mm Ø) kg 4.00 - 481.00
Support Top Bars (0mm Ø) kg 0.00 - 0.00
Links (8mm Ø) kg 197.69 - 25,699.26
Total Reinforcement Cost 205.09 26,661.06
Labor & Formwork
Labor Sum 1 - 35,568.32
Formwork Sum 1 - 16,000.00
Total Material Cost 118,561.06
Grand Total 154,129.37
Beam: Beam 1 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 10.50 - -
Cement Bags Bags 43.20 - -
Fine Aggregates (Sand) Lorry 1.13 - -
Coarse Aggregates (Ballast) Lorry 1.13 - -
Concrete Cost - - - 132,825.00
Reinforcement
Main Bars (10mm Ø) kg 4.00 - 481.00
Support Bottom Bars (0mm Ø) kg 0.00 - 0.00
Top Bars (10mm Ø) kg 4.00 - 481.00
Support Top Bars (0mm Ø) kg 0.00 - 0.00
Links (8mm Ø) kg 336.07 - 43,688.74
Total Reinforcement Cost 343.47 44,650.54
Labor & Formwork
Labor Sum 1 - 59,242.66
Formwork Sum 1 - 20,000.00
Total Material Cost 197,475.54
Grand Total 256,718.20

Total Cost for All Beams: Ksh 410,847.57

Columns

No columns created.

Hipped Roofs

No hipped roof data available.

Gable Roof

Project ID Item Description Unit Quantity Unit Rate (Ksh) Total (Ksh) Actions
46 1 Truss Materials m 176,677.27 150.00 26,501.59
2 Purlins m 1,000.00 100.00 7,200.00
3 Roofing Sheets (79 pcs) pcs 79 1,500.00 118,518.52
4 Labor sum 1 45,666.03 45,666.03
Grand Total - Truss Cost Ksh 26,501.59
Grand Total - Purlins Ksh 7,200.00
Grand Total - Roofing Sheets Ksh 118,518.52
Grand Total - Labor Ksh 45,666.03
Overall Gable Roof Total Ksh 197,886.14

Grand Total Cost Summary

Grand Cement Bags:

386.75

Grand Fine Agg (Sand) FSR Lorry:

Ksh 10.07

Grand Coarse Agg (Ballast) FSR Lorry:

Ksh 3.44

Grand Concrete Cost:

Ksh 269,445.00

Grand Bars Cost:

Ksh 71,311.59

Grand Labor Cost:

Ksh 468,075.04


Grand Total Cost

Ksh 2,028,325.19