Menu

Bill of Quantities

Foundations

Walls

Add Wall Item

No walls created yet. Click "Add Wall Item" to get started.

Interior Walls With Doors

No interior walls created.

Total Walls Analysis (Including Exterior Walls)

Total Cement Bags: 0.00

Total Fine Aggregate (FSR Lorry): 0.00

Total Bricks: 0.00

Total Bricks Cost: Ksh0.00

Total Mortar Cost: Ksh0.00

Total Walls Cost: Ksh0.00

Slab Panels

# Work Item Specifications Unit Quantity Unit Cost (Ksh) Total (Ksh) Actions
1 Concrete (53.90 m³) Cement: 221.76 bags
Sand: 5.78 lorries
Ballast: 5.78 lorries
53.90 12,650.00 681,835.00

Reinforcement Ø8mm, Total: 7,465.55m
Weight: 2,945.79 kg
kg 2,945.79 190.00 559,699.25
Labor Mixing, placing, finishing lot 1 422,356.28 422,356.28
Formwork For slab edges and soffit - - 166,320.00
2 Concrete (21.00 m³) Cement: 86.40 bags
Sand: 2.25 lorries
Ballast: 2.25 lorries
21.00 12,650.00 265,650.00

Reinforcement Ø8mm, Total: 2,917.20m
Weight: 1,151.08 kg
kg 1,151.08 190.00 218,705.31
Labor Mixing, placing, finishing lot 1 164,746.59 164,746.59
Formwork For slab edges and soffit - - 64,800.00
Grand Total (Ksh): 2,544,112.43

Beams

Create Beam
Beam: FFBM1 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.98 - -
Cement Bags Bags 4.02 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.98 15,500.00 15,159.00
Reinforcement
Main Bars (12mm Ø) bars 1.42 - 3,019.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 7.38 - 6,986.77
Total Reinforcement Cost kg 65.12 200.00 13,023.90
Labor & Formwork
Labor Sum 1 - 10,303.29
Formwork Sum 1 - 6,161.40
Total Material Cost 34,344.30
Grand Total 44,647.59
Beam: FFBM2 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 1.96 - -
Cement Bags Bags 8.05 - -
Fine Aggregates (Sand) Lorry 0.21 - -
Coarse Aggregates (Ballast) Lorry 0.21 - -
Concrete Cost 1.96 15,500.00 30,318.00
Reinforcement
Main Bars (20mm Ø) bars 2.83 - 16,770.00
Support Bottom Bars (20mm Ø) bars 2.83 - 16,770.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (12mm Ø) bars 1.42 - 3,019.00
Links (10mm Ø) bars 7.65 - 11,325.79
Total Reinforcement Cost kg 254.51 200.00 50,902.57
Labor & Formwork
Labor Sum 1 - 26,874.74
Formwork Sum 1 - 8,361.90
Total Material Cost 89,582.47
Grand Total 116,457.22
Beam: FFBM1 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.98 - -
Cement Bags Bags 4.02 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.98 15,500.00 15,159.00
Reinforcement
Main Bars (12mm Ø) bars 1.42 - 3,019.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 7.38 - 6,986.77
Total Reinforcement Cost kg 65.12 200.00 13,023.90
Labor & Formwork
Labor Sum 1 - 10,303.29
Formwork Sum 1 - 6,161.40
Total Material Cost 34,344.30
Grand Total 44,647.59
Beam: FFBM3 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.98 - -
Cement Bags Bags 4.02 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.98 15,500.00 15,159.00
Reinforcement
Main Bars (12mm Ø) bars 1.42 - 3,019.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 7.38 - 6,986.77
Total Reinforcement Cost kg 65.12 200.00 13,023.90
Labor & Formwork
Labor Sum 1 - 10,303.29
Formwork Sum 1 - 6,161.40
Total Material Cost 34,344.30
Grand Total 44,647.59
Beam: FFBM4 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 3.70 - -
Cement Bags Bags 15.21 - -
Fine Aggregates (Sand) Lorry 0.40 - -
Coarse Aggregates (Ballast) Lorry 0.40 - -
Concrete Cost 3.70 15,500.00 57,288.00
Reinforcement
Main Bars (20mm Ø) bars 8.25 - 48,830.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (20mm Ø) bars 8.25 - 48,830.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 27.51 - 26,053.07
Total Reinforcement Cost kg 618.56 200.00 123,712.62
Labor & Formwork
Labor Sum 1 - 61,285.63
Formwork Sum 1 - 23,284.80
Total Material Cost 204,285.42
Grand Total 265,571.04
Beam: FFBM4B (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 3.70 - -
Cement Bags Bags 15.21 - -
Fine Aggregates (Sand) Lorry 0.40 - -
Coarse Aggregates (Ballast) Lorry 0.40 - -
Concrete Cost 3.70 15,500.00 57,288.00
Reinforcement
Main Bars (16mm Ø) bars 5.50 - 20,834.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (16mm Ø) bars 5.50 - 20,834.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 20.67 - 19,571.37
Total Reinforcement Cost kg 306.20 200.00 61,239.44
Labor & Formwork
Labor Sum 1 - 42,543.67
Formwork Sum 1 - 23,284.80
Total Material Cost 141,812.24
Grand Total 184,355.92
Beam: FFBM5 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.92 - -
Cement Bags Bags 3.80 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.92 15,500.00 14,322.00
Reinforcement
Main Bars (12mm Ø) bars 1.33 - 2,841.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.33 - 2,841.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 5.27 - 4,987.54
Total Reinforcement Cost kg 53.35 200.00 10,669.55
Labor & Formwork
Labor Sum 1 - 9,243.83
Formwork Sum 1 - 5,821.20
Total Material Cost 30,812.75
Grand Total 40,056.58
Beam: FFBM6 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.98 - -
Cement Bags Bags 4.02 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.98 15,500.00 15,159.00
Reinforcement
Main Bars (12mm Ø) bars 1.42 - 3,019.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 5.57 - 5,271.64
Total Reinforcement Cost kg 56.54 200.00 11,308.78
Labor & Formwork
Labor Sum 1 - 9,788.75
Formwork Sum 1 - 6,161.40
Total Material Cost 32,629.18
Grand Total 42,417.93
Beam: FFBM7 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 1.96 - -
Cement Bags Bags 8.05 - -
Fine Aggregates (Sand) Lorry 0.21 - -
Coarse Aggregates (Ballast) Lorry 0.21 - -
Concrete Cost 1.96 15,500.00 30,318.00
Reinforcement
Main Bars (20mm Ø) bars 2.83 - 16,770.00
Support Bottom Bars (20mm Ø) bars 2.83 - 16,770.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (12mm Ø) bars 1.42 - 3,019.00
Links (8mm Ø) bars 10.14 - 9,606.81
Total Reinforcement Cost kg 245.92 200.00 49,183.58
Labor & Formwork
Labor Sum 1 - 26,359.05
Formwork Sum 1 - 8,361.90
Total Material Cost 87,863.48
Grand Total 114,222.53
Beam: FFBM8 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 1.44 - -
Cement Bags Bags 5.92 - -
Fine Aggregates (Sand) Lorry 0.15 - -
Coarse Aggregates (Ballast) Lorry 0.15 - -
Concrete Cost 1.44 15,500.00 22,320.00
Reinforcement
Main Bars (20mm Ø) bars 3.25 - 19,236.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (16mm Ø) bars 3.25 - 12,311.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 8.13 - 7,702.28
Total Reinforcement Cost kg 196.25 200.00 39,249.27
Labor & Formwork
Labor Sum 1 - 21,192.38
Formwork Sum 1 - 9,072.00
Total Material Cost 70,641.27
Grand Total 91,833.66
Beam: FFBM9 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.98 - -
Cement Bags Bags 4.02 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.98 15,500.00 15,159.00
Reinforcement
Main Bars (12mm Ø) bars 1.42 - 3,019.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 5.57 - 5,271.64
Total Reinforcement Cost kg 56.54 200.00 11,308.78
Labor & Formwork
Labor Sum 1 - 9,788.75
Formwork Sum 1 - 6,161.40
Total Material Cost 32,629.18
Grand Total 42,417.93
Beam: FFBM10 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 1.96 - -
Cement Bags Bags 8.05 - -
Fine Aggregates (Sand) Lorry 0.21 - -
Coarse Aggregates (Ballast) Lorry 0.21 - -
Concrete Cost 1.96 15,500.00 30,318.00
Reinforcement
Main Bars (20mm Ø) bars 2.83 - 16,770.00
Support Bottom Bars (20mm Ø) bars 2.83 - 16,770.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (12mm Ø) bars 1.42 - 3,019.00
Links (8mm Ø) bars 12.14 - 11,493.44
Total Reinforcement Cost kg 255.35 200.00 51,070.22
Labor & Formwork
Labor Sum 1 - 26,925.04
Formwork Sum 1 - 8,361.90
Total Material Cost 89,750.12
Grand Total 116,675.16
Beam: FFBM7 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 1.96 - -
Cement Bags Bags 8.05 - -
Fine Aggregates (Sand) Lorry 0.21 - -
Coarse Aggregates (Ballast) Lorry 0.21 - -
Concrete Cost 1.96 15,500.00 30,318.00
Reinforcement
Main Bars (20mm Ø) bars 2.83 - 16,770.00
Support Bottom Bars (20mm Ø) bars 2.83 - 16,770.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (12mm Ø) bars 1.42 - 3,019.00
Links (8mm Ø) bars 10.14 - 9,606.81
Total Reinforcement Cost kg 245.92 200.00 49,183.58
Labor & Formwork
Labor Sum 1 - 26,359.05
Formwork Sum 1 - 8,361.90
Total Material Cost 87,863.48
Grand Total 114,222.53
Beam: FFBM6 (ID: 46)
Item Description Unit Quantity Rate (Ksh) Total (Ksh)
Concrete Works
Concrete Volume 0.98 - -
Cement Bags Bags 4.02 - -
Fine Aggregates (Sand) Lorry 0.10 - -
Coarse Aggregates (Ballast) Lorry 0.10 - -
Concrete Cost 0.98 15,500.00 15,159.00
Reinforcement
Main Bars (12mm Ø) bars 1.42 - 3,019.00
Support Bottom Bars (0mm Ø) bars 0.00 - 0.00
Top Bars (12mm Ø) bars 1.42 - 3,019.00
Support Top Bars (0mm Ø) bars 0.00 - 0.00
Links (8mm Ø) bars 5.57 - 5,271.64
Total Reinforcement Cost kg 56.54 200.00 11,308.78
Labor & Formwork
Labor Sum 1 - 9,788.75
Formwork Sum 1 - 6,161.40
Total Material Cost 32,629.18
Grand Total 42,417.93

Total Cost for All Beams: Ksh 1,304,591.21

Columns

No columns created.

Hipped Roofs

No hipped roof data available.

Gable Roof

Project ID Item Description Unit Quantity Unit Rate (Ksh) Total (Ksh) Actions
46 1 Truss Materials m 428,000.00 150.00 64,200.00
2 Purlins m 800.00 100.00 22,200.00
3 Roofing Sheets (338 pcs) pcs 338 800.00 270,419.75
4 Labor sum 1 107,045.93 107,045.93
Grand Total - Truss Cost Ksh 64,200.00
Grand Total - Purlins Ksh 22,200.00
Grand Total - Roofing Sheets Ksh 270,419.75
Grand Total - Labor Ksh 107,045.93
Overall Gable Roof Total Ksh 463,865.68

Grand Total Cost Summary

Grand Cement Bags:

404.63

Grand Fine Agg (Sand) FSR Lorry:

Ksh 10.54

Grand Coarse Agg (Ballast) FSR Lorry:

Ksh 10.54

Grand Concrete Cost:

Ksh 1,310,929.00

Grand Bars Cost:

Ksh 1,286,613.46

Grand Labor Cost:

Ksh 995,208.30


Grand Total Cost

Ksh 4,312,569.32